Roads19DQ0141

CONSTRUCTION OF ROAD AT GREENVALLEY, SAN NICOLAS 3, BACOOR, CAVITE AND CONCRETING OF ROAD AT GREENVALLEY IN BRGY. SAN NICOLAS 3, BACOOR, CAVITE

CONSTRUCTION OF ROAD AT GREENVALLEY, SAN NICOLAS 3, BACOOR, CAVITE AND CONCRETING OF ROAD AT GREENVALLEY IN BRGY. SAN NICOLAS 3, BACOOR, CAVITE is a DPWH-tracked public work in Cavite 3rd DEO, Region IV-A. Reported contract value: ₱10,614,968.28. Status: Reported complete (DPWH). Contractor on record: AARCON BUILDERS. Figures trace to dpwh.

Cavite 3rd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-B-19-0012958

₱46,889,208.00 · FY2019

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

386 projects · ₱11.2B total · 0 flags

Other projects by this contractor

DREDGING OF GUAGUA-PASAC RIVER, SASMUAN, PAMPANGA

Flood Control Management Cluster, Central Office

2018₱187.5M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION - PREVENTIVE MAINTENANCE - PRIMARY ROADS - EPIFANIO DELOS SANTOS AVE (EDSA) - K0021 + (-158) - K0021 + 000, K0021 + (-229) - K0021 + (-158), K0021 + 000 - K0025 + 163

National Capital Region, National Capital Region

2024₱160.5M
Reported complete (DPWH)
No sat.

PREVENTIVE MAINTENANCE - PRIMARY ROADS - MANILA-CAVITE (NCR BDRY-JCT CAVITE CITY SECT) - K0015 + 985 - K0016 + 087, K0016 + 303 - K0016 + 651; MC DONALD JCT-AGUINALDO H-WAY - K0015 + 274 - K0015 + 690 AND MANILA-CAVITE (NCR BDRY-JCT CAVITE CITY SECT) - K

Cavite 3rd DEO, Region IV-A

2025₱140.9M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMASSET PRESERVATION PROGRAMREHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADSKAWIT-NOVELETA DIV RD. - K0024 + 495 - K0025 + 438

Cavite 1st DEO, Region IV-A

2025₱103.9M
Reported complete (100% progress, DPWH status On-Going)

PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS CONSTRUCTION OF BACOOR FLOOD CONTROL PROJECT INCL. A PUMPING STATION, (PACKAGE A), BACOOR CITY, CAVITE

Region IV-A, Region IV-A

2019₱103.0M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - ASPHALT OVERLAY OF TANAY-SAMPALOC RD - K0066+100 - K0068+000, K0069+000 - K0070+443, TANAY, RIZAL

Rizal 2nd DEO, Region IV-A

2024₱98.0M
Reported complete (DPWH)
View all 386 projects →

4. Implementation

Contract Amount

₱10,614,968.28

Progress

Reported complete (DPWH)

Start Date

December 2, 2020

Target End

March 31, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.