Buildings and Facilities19OE0107

LOCAL PROGRAM - LOCAL INFRASTRUCTURE PROGRAM - BUILDINGS AND OTHER STRUCTURES -MULTI - PURPOSE / FACILITIES - IMPROVEMENT OF MULTI - PURPOSE BUILDING, BARANGAY 618, ZONE 61,BACOOD, STA. MESA, MANILA

LOCAL PROGRAM - LOCAL INFRASTRUCTURE PROGRAM - BUILDINGS AND OTHER STRUCTURES -MULTI - PURPOSE / FACILITIES - IMPROVEMENT OF MULTI - PURPOSE BUILDING, BARANGAY 618, ZONE 61,BACOOD, STA. MESA, MANILA is a DPWH-tracked public work in North Manila DEO, National Capital Region. Reported contract value: ₱1,907,090.02. Status: Reported complete (DPWH). Contractor on record: ALE BUILDERS CONST AND DEVELOPMENT CORP. Figures trace to dpwh.

North Manila DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-A-19-0005535

₱3,306,000.00 · FY2019

Released to Regional Office - XI (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

101 projects · ₱1.7B total · 1 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-TERTIARY ROADS-SOUTH SUPER H-WAY WEST SERVICE RD-K0011+(-384)-K0012+544

South Manila DEO, National Capital Region

2025₱121.1M
Reported complete (100% progress, DPWH status On-Going)
No sat.

1. CONSTRUCTION OF MULTI-PURPOSE BUILDING, PLAZA MORGA, TONDO, MANILA CITY 2. CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE 2), PLAZA MORGA, TONDO, MANILA3. CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE 3), PLAZA MORGA,

North Manila DEO, National Capital Region

2023₱108.2M
Reported complete (DPWH)
No sat.

IMPROVEMENT OF DRAINAGE SYSTEM AT LIWASANG IPIL-IPIL (CCP OPEN GROUNDS), CCP COMPLEX, PASAY CITY

South Manila DEO, National Capital Region

2025₱94.3M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM-LOCAL INFRASTRUCTURE PROGRAM-BLDGS & OTHER STRUCTURES-SCHOOL BLDGS-CONST OF 2 UNITS OF

South Manila DEO, National Capital Region

2020₱62.4M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-ACCESS ROADS AND/OR BRIDGES FROM THE NAT'L. ROAD/S LEADING TO MAJOR STRATEGIC PUBLIC BUILDINGS/FACILITIES-IMPV'T. OF ROAD INCLUDING SIDEWALK WITH STREETLIGHTS, ZONE 83 TO ZONE 89,

South Manila DEO, National Capital Region

2022₱49.5M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM-LOCAL INFRASTRUCTURE PROGRAM-LOCAL ROADS AND BRIDGES-LOCAL ROADS-IMPROVEMENT OF SIDEWALK WITH STREETLIGHTS, ZONE 83-89, DISTRICT 5, MANILA

South Manila DEO, National Capital Region

2021₱49.5M
Reported complete (DPWH)
View all 101 projects →

4. Implementation

Contract Amount

₱1,907,090.02

Progress

Reported complete (DPWH)

Start Date

June 17, 2019

Target End

October 14, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.