Roads19CE0025

NETWORK DEVELOPMENT - OFF-CARRIAGEWAY IMPROVEMENT - PRIMARY ROADS - DAANG MAHARLIKA (LZ) K0147+100 - K0147+400

NETWORK DEVELOPMENT - OFF-CARRIAGEWAY IMPROVEMENT - PRIMARY ROADS - DAANG MAHARLIKA (LZ) K0147+100 - K0147+400 is a DPWH-tracked public work in Nueva Ecija 1st DEO, Region III. Reported contract value: ₱2,871,531.09. Status: Reported complete (DPWH). Contractor on record: ADROIT EJD CONST CORP FORMERLY: ADROIT CONST. Figures trace to dpwh.

Nueva Ecija 1st DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-F-19-0010558

₱153,529.00 · FY2019

Released to MSU-Tawi-Tawi College of Ms Technology and Oceanography (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱2,871,531.09

Progress

Reported complete (DPWH)

Start Date

June 17, 2019

Target End

August 15, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.