Flood Control and Drainage23J00105

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL PROJECT AT REBOKON RIVER, REBOKON BRIDGE SECTION ALONG ZAMBOANGA DEL SUR COASTAL NATIONAL ROAD (S01101MN), BARANGAY REBOKON, DUMALINAO, ZAMBOANGA

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL PROJECT AT REBOKON RIVER, REBOKON BRIDGE SECTION ALONG ZAMBOANGA DEL SUR COASTAL NATIONAL ROAD (S01101MN), BARANGAY REBOKON, DUMALINAO, ZAMBOANGA is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱48,140,909.67. Status: Past target date (DPWH On-Going). Contractor on record: GENETIAN BUILDERS AND ENT INC FORMERLY: GENETIAN BUILDERS. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱48,140,909.67

Progress

Past target date (DPWH On-Going)

Start Date

July 21, 2023

Target End

January 7, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.