Construction of Flood Mitigation Structure24KG0011

Construction of Limuag CIS Protection Dike, Baroy, Lanao Del Norte

Construction of Limuag CIS Protection Dike, Baroy, Lanao Del Norte is a DPWH-tracked public work in BAROY (LANAO DEL NORTE), LANAO DEL NORTE, Region X. Reported contract value: ₱12,250,000.00. Status: Reported complete (DPWH). Contractor on record: PRIME HAUS BUILDERS & ENT. Figures trace to sumbong.

BAROY (LANAO DEL NORTE), LANAO DEL NORTE, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Brgy. Big Banisilon, Tangcal, Lanao del Norte
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROX-24-0002871

₱30,000,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROX-24-0008335

₱1,504,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROX-24-0008336

₱139,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1 projects · ₱12.3M total · 0 flags

4. Implementation

Contract Amount

₱12,250,000.00

Progress

Reported complete (DPWH)

Start Date

January 23, 2024

Target End

August 23, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.