Flood Control and Drainage20NG0053

CONSTRUCTION OF SICO-SICO FLOOD CONTROL / BRGY. SICO-SICO, GIGAQUIT, SURIGAO DEL NORTE

CONSTRUCTION OF SICO-SICO FLOOD CONTROL / BRGY. SICO-SICO, GIGAQUIT, SURIGAO DEL NORTE is a DPWH-tracked public work in Surigao del Norte 2nd DEO, Region XIII. Reported contract value: ₱27,929,390.07. Status: Reported complete (DPWH). Contractor on record: JMT CONST. Figures trace to dpwh.

Surigao del Norte 2nd DEO, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱27,929,390.07

Progress

Reported complete (DPWH)

Start Date

December 10, 2020

Target End

August 12, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.