Construction of Flood Mitigation Structure23OE0042

Construction of Retarding Basin at Estero dela Reina, Barangay 290, Manila City

Construction of Retarding Basin at Estero dela Reina, Barangay 290, Manila City is a DPWH-tracked public work in CITY OF MANILA (METROPOLITAN MANILA), CITY OF MANILA, National Capital Region. Reported contract value: ₱94,716,532.95. Status: Reported complete (DPWH). Contractor on record: ST TIMOTHY CONST CORP / ALLEYWAY CONST. Figures trace to sumbong.

CITY OF MANILA (METROPOLITAN MANILA), CITY OF MANILA, National Capital Region
Region: National Capital Region
Skipped: this map coordinate is shared by many projects, so the pin may not mark the exact worksite.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱40,343,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Mitigation Structure, Easement Road Estero de Pandacan (Tripa de Gallina - P. Quirino Ave.) Manila
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

North Manila District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1 projects · ₱94.7M total · 0 flags

4. Implementation

Contract Amount

₱94,716,532.95

Progress

Reported complete (DPWH)

Start Date

February 17, 2023

Target End

August 5, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.