Buildings and Facilities17HH0002

CONSTRUCTION / EXPANSION OF NBI VII OFFICE BUILDING AT CAPITOL SITE, CEBU CITY

CONSTRUCTION / EXPANSION OF NBI VII OFFICE BUILDING AT CAPITOL SITE, CEBU CITY is a DPWH-tracked public work in Cebu City DEO, Region VII. Reported contract value: ₱6,970,464.89. Status: Reported complete (DPWH). Contractor on record: JTL CONSTRUCTIION. Figures trace to dpwh.

Cebu City DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control and Mitigation Structures along Guadalupe River, Brgy. Capitol Site, Cebu City
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-D-17-0022755

₱2,108,129.00 · FY2017

Released to Philippine Air For ( Air Forces ) (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱6,970,464.89

Progress

Reported complete (DPWH)

Start Date

March 30, 2017

Target End

September 25, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.