GAA 2024 OO-124DJ0047

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF MISSING LINKS/NEW ROADS, QUEZON ECO-TOURISM-SARIAYA-CANDELARIA-TIAONG-SAN ANTONIO ROAD, CONSTRUCTION OF CABAY BRIDGE, QUEZON

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF MISSING LINKS/NEW ROADS, QUEZON ECO-TOURISM-SARIAYA-CANDELARIA-TIAONG-SAN ANTONIO ROAD, CONSTRUCTION OF CABAY BRIDGE, QUEZON is a DPWH-tracked public work in Quezon 2nd DEO, Region IV-A. Reported contract value: ₱67,550,000.00. Status: Past target date (DPWH On-Going). Contractor on record: WAYCON BUILDERS AND CONST SUPPLY CORP FOR:WAYCON BUILDERS. Figures trace to dpwh.

Quezon 2nd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Brgy. Ibabang Dupay, Lucena City, Quezon Province
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Quezon 2nd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

24DJ0047

₱66,030,125.00 · WAYCON BUILDERS & CONSTRUCTION SUPPLY

4. Implementation

Contract Amount

₱67,550,000.00

Progress

Past target date (DPWH On-Going)

Start Date

April 18, 2024

Target End

April 12, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.