Flood Control and Drainage23AA0157

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - REHABILITATION OF DAMAGED CONCRETE BANK REVETMENT WITH STEEL SHEET PILES, ALONG PADSAN RIVER REVETMENT, BARANGAY 8, SARRAT, ILOCOS NORTE

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - REHABILITATION OF DAMAGED CONCRETE BANK REVETMENT WITH STEEL SHEET PILES, ALONG PADSAN RIVER REVETMENT, BARANGAY 8, SARRAT, ILOCOS NORTE is a DPWH-tracked public work in Ilocos Norte 1st DEO, Region I. Reported contract value: ₱19,599,583.81. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: BJMJB CONST. Figures trace to dpwh.

Ilocos Norte 1st DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Project along Sarrat Padsan River Basin, Barangay 8 San Antonio and Barangay 9 San Lorenzo, Sarrat, Ilocos Norte
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Ilocos Norte 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

360 projects · ₱4.5B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD MITIGATING STRUCTURE RIGHT BANK, BARANGAY ISIC-ISIC, VINTAR ILOCOS NORTE (PHASE 2)

Ilocos Norte 1st DEO, Region I

2024₱57.9M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATIONSTRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OFFLOOD CONTROL STRUCTURE ALONG PADSAN RIVER, BARANGAY10, SARRAT, ILOCOS NORTE (PHASE 2)

Ilocos Norte 1st DEO, Region I

2024₱57.9M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BISLAK RIVER, SITIO DALIM, BARANGAY CABAYO, VINTAR, ILOCOS NORTE

Ilocos Norte 1st DEO, Region I

2025₱56.4M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BISLAK RIVER, SANJERA BENGBENGKAG, BARANGAY ISIC-ISIC, VINTAR, ILOCOS NORTE

Ilocos Norte 1st DEO, Region I

2025₱56.1M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG DAURAO CREEK, BARANGAY CAAOACAN, LAOAG CITY, ILOCOS NORTE

Ilocos Norte 1st DEO, Region I

2025₱55.6M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE MANGATO BRIDGE UPSTREAM, LAOAG CITY, ILOCOS NORTE

Ilocos Norte 1st DEO, Region I

2025₱55.6M
Past target date (DPWH On-Going)
View all 360 projects →

4. Implementation

Contract Amount

₱19,599,583.81

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

March 29, 2023

Target End

October 15, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.