Water Provision and Storage20DD0103

LOCAL PROGRAM, LOCAL INFRASTRUCTURE PROGRAM, WATER MANAGEMENT FACILITIES, WATER SUPPLY, CONSTRUCTION OF WATER SYSTEM AT PINAGKAWITAN INTEGRATED NATIONAL HIGH SCHOOL AT BARANGAY PINAGKAWITAN, LIPA CITY, BATANGAS

LOCAL PROGRAM, LOCAL INFRASTRUCTURE PROGRAM, WATER MANAGEMENT FACILITIES, WATER SUPPLY, CONSTRUCTION OF WATER SYSTEM AT PINAGKAWITAN INTEGRATED NATIONAL HIGH SCHOOL AT BARANGAY PINAGKAWITAN, LIPA CITY, BATANGAS is a DPWH-tracked public work in Batangas 4th DEO, Region IV-A. Reported contract value: ₱2,880,896.73. Status: Reported complete (DPWH). Contractor on record: VRV CONST AND TRADING. Figures trace to dpwh.

Batangas 4th DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation/Improvement of Flood Control Structure at Brgy. Tambo, Lipa City, Batangas
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Batangas 4th DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

195 projects · ₱2.0B total · 0 flags

Other projects by this contractor

No sat.

LOCAL PROGRAM, LOCAL INFRASTRUCTURE PROGRAM, BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/ FACILITIES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE 2), PADRE GARCIA COMMUNITY HOSPITAL, PADRE GARCIA, BATANGAS

Batangas 4th DEO, Region IV-A

2021₱96.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BOLBOK INTEGRATED NATIONAL HIGH SCHOOL, BARANGAY BOLBOK, LIPA CITY, BATA

Batangas 4th DEO, Region IV-A

2024₱78.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TALISAY, LIPA CITY, BATANGAS

Batangas 4th DEO, Region IV-A

2024₱57.6M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM, LOCAL INFRASTRUCTURE PROGRAM, BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/ FACILITIES, CONSTRUCTION/ COMPLETION OF MULTI-PURPOSE BUILDING (COMMUNITY HOSPITAL) AT BRGY. CASTILLO, PADRE GARCIA, BATANGAS

Batangas 4th DEO, Region IV-A

2020₱38.4M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM, LOCAL INFRASTRUCTURE PROGRAM, BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/ FACILITIES, CONSTRUCTION OF MULTI-PURPOSE BUILDING AT MAXIMO T. HERNANDEZ MEMORIAL NATIONAL HIGH SCHOOL AND MALAININ ELEMENTARY SCHOOL, IBAAN, BATANGAS

Batangas 4th DEO, Region IV-A

2020₱38.4M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM, CONSTRUCTION/ REPAIR/ REHABILITATION/ IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/ FACILITIES, CONSTRUCTION OF MULTI- PURPOSE BUILDING (BUREAU OF FIRE), LIPA CITY, BATANGAS

Batangas 4th DEO, Region IV-A

2020₱38.0M
Reported complete (DPWH)
View all 195 projects →

4. Implementation

Contract Amount

₱2,880,896.73

Progress

Reported complete (DPWH)

Start Date

October 13, 2020

Target End

January 10, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.