Construction of Flood Mitigation Structure24IC0076

Construction of Flood Control Structure along San Isidro River, Barangay Libertad, Palo, Leyte

Construction of Flood Control Structure along San Isidro River, Barangay Libertad, Palo, Leyte is a DPWH-tracked public work in PALO (LEYTE), LEYTE, Region VIII. Reported contract value: ₱41,469,137.10. Status: Reported complete (DPWH). Contractor on record: AQUALINE CONST CORP FORMERLY: AQUALINE CONST. Figures trace to sumbong.

PALO (LEYTE), LEYTE, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Mainit River, Barangay Cavite, Alangalang, Leyte
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-24-0008481

₱1,388,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-24-0008493

₱128,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

245 projects · ₱18.1B total · 0 flags

4. Implementation

Contract Amount

₱41,469,137.10

Progress

Reported complete (DPWH)

Start Date

April 23, 2024

Target End

October 30, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.