Roads18CD0320

CONCRETING OF GULOD NA ATIS, BRGY. BUHOL NA MANGGA FMR, BRGY. BUHOL NA MANGGA, SAN ILDEFONSO, BULACAN

CONCRETING OF GULOD NA ATIS, BRGY. BUHOL NA MANGGA FMR, BRGY. BUHOL NA MANGGA, SAN ILDEFONSO, BULACAN is a DPWH-tracked public work in Bulacan 2nd DEO, Region III. Reported contract value: ₱4,775,349.42. Status: Reported complete (DPWH). Contractor on record: ST MATTHEW GEN CONTRACTOR. Figures trace to dpwh.

Bulacan 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Maasim River, San Rafael and San Ildefonso, Bulacan
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIX-18-0034392

₱139,000.00 · FY2018

Released to Zamboanga del Norte 3rd 201 District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,775,349.42

Progress

Reported complete (DPWH)

Start Date

November 12, 2018

Target End

February 9, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.