Flood Control and Drainage24EH0173

CONSTRUCTION OF LUMBANG ESTE FLOOD CONTROL STRUCTURE ALONG LUMBANG RIVER PHASE 2, CAJIDIOCAN, ROMBLON

CONSTRUCTION OF LUMBANG ESTE FLOOD CONTROL STRUCTURE ALONG LUMBANG RIVER PHASE 2, CAJIDIOCAN, ROMBLON is a DPWH-tracked public work in Romblon DEO, Region IV-B. Reported contract value: ₱135,097,581.25. Status: Reported complete (DPWH). Contractor on record: SUNWEST INC FORMERLY: SUNWEST CONST. Figures trace to dpwh.

Romblon DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Canlumay Flood Control Structure, Odiongan, Romblon
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Romblon DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Construction of Flood Control Structure

₱133,081,607.75 · SUNWEST, .

Contractor

738 projects · ₱73.0B total · 0 flags

Other projects by this contractor

No sat.

CLUSTER 1: BASIC INFRASTRUCTURE PROGRAM (BIP) - COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION - CONSTRUCTION OF CAUSEWAY, SUBSECTION 3.2A, TACLOBAN CITY, LEYTE ; AND OTHER FIVE (5) PROJECTS

Region VIII, Region VIII

2024₱1.3B
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF STORM SURGE PROTECTION/TIDE EMBANKMENT, LEYTE

Region VIII, Region VIII

2023₱1.1B
Past target date (DPWH On-Going)
No sat.

CLUSTER 2: PROJECT 1. CONST. OF CAUSEWAY, SECT. 3.1, STA. 0+140-STA. 0+233, TAC. CITY, LEYTE; PROJECT 2. CONST. OF CAUSEWAY, SECT. 3.2, STA. 0+233-STA.0+305, TAC. CITY, LEYTE; PROJECT 3. CONST. OF CAUSEWAY, SECT. 3.3, STA. 0+400-STA. 0+448, TAC. CITY, LEY

Region VIII, Region VIII

2022₱511.9M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM- CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE MUMPONG RIVER, TUBAN-BATONG BUHAY, BRGY. TUBAN, SABLAYAN, OCC. MINDORO

Region IV-B, Region IV-B

2025₱291.8M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM- CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, MUMPONG RIVER, TUBAN-STA. LUCIA, BRGY. TUBAN, SABLAYAN, OCC. MINDORO

Region IV-B, Region IV-B

2025₱291.5M
Past target date (DPWH On-Going)

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-INTERJURISDICTIONAL ROADS AND/OR BRIDGES(OR, ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)-CONSTRUCTION OF ROAD,MIISI-BONGA-BUYUAN-LIDONG-DARAGA,DARAGA/

Region V, Region V

2022₱288.5M
Reported complete (100% progress, DPWH status On-Going)
View all 738 projects →

4. Implementation

Contract Amount

₱135,097,581.25

Progress

Reported complete (DPWH)

Start Date

January 13, 2025

Target End

January 4, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.