GAA 2022 CSSP22I00102

CLUSTER 2: PROJECT 1. CONST. OF CAUSEWAY, SECT. 3.1, STA. 0+140-STA. 0+233, TAC. CITY, LEYTE; PROJECT 2. CONST. OF CAUSEWAY, SECT. 3.2, STA. 0+233-STA.0+305, TAC. CITY, LEYTE; PROJECT 3. CONST. OF CAUSEWAY, SECT. 3.3, STA. 0+400-STA. 0+448, TAC. CITY, LEY

CLUSTER 2: PROJECT 1. CONST. OF CAUSEWAY, SECT. 3.1, STA. 0+140-STA. 0+233, TAC. CITY, LEYTE; PROJECT 2. CONST. OF CAUSEWAY, SECT. 3.2, STA. 0+233-STA.0+305, TAC. CITY, LEYTE; PROJECT 3. CONST. OF CAUSEWAY, SECT. 3.3, STA. 0+400-STA. 0+448, TAC. CITY, LEY is a DPWH-tracked public work in Region VIII, Region VIII. Reported contract value: ₱511,892,618.99. Status: Past target date (DPWH On-Going). Contractor on record: SUNWEST INC FORMERLY: SUNWEST CONST. Figures trace to dpwh.

Region VIII, Region VIII
Region: Region VIII

Follow the peso

2 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱511,892,619 · SUNWEST, .

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    83% reported · imagery 2021-06-16 → 2025-04-09

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CLUSTER 2: PROJECT 1. CONST. OF CAUSEWAY, SECT. 3.1, STA. 0+140-STA. 0+233, TAC. CITY, LEYTE; PROJECT 2. CONST. OF CAUSEWAY, SECT. 3.2, STA. 0+233-STA.0+305, TAC. CITY, LEYTE; PROJECT 3. CONST. OF CAUSEWAY, SECT. 3.3, STA. 0+400-STA. 0+448, TAC. CITY, LEY

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2022 GAA. DBM GAA FY2022

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

Confirmed (exact contract ID) · 100%

CID No. 22I00102 (Re-Advertisement)

₱511,892,618.99 · SUNWEST, .

Award / contract ref: CID No. 22I00102 (Re-Advertisement)

Contractor

D

738 projects · ₱73.0B total · 0 flags

Other projects by this contractor

No sat.

CLUSTER 1: BASIC INFRASTRUCTURE PROGRAM (BIP) - COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION - CONSTRUCTION OF CAUSEWAY, SUBSECTION 3.2A, TACLOBAN CITY, LEYTE ; AND OTHER FIVE (5) PROJECTS

Region VIII, Region VIII

2024₱1.3B
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF STORM SURGE PROTECTION/TIDE EMBANKMENT, LEYTE

Region VIII, Region VIII

2023₱1.1B
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM- CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE MUMPONG RIVER, TUBAN-BATONG BUHAY, BRGY. TUBAN, SABLAYAN, OCC. MINDORO

Region IV-B, Region IV-B

2025₱291.8M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM- CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, MUMPONG RIVER, TUBAN-STA. LUCIA, BRGY. TUBAN, SABLAYAN, OCC. MINDORO

Region IV-B, Region IV-B

2025₱291.5M
Past target date (DPWH On-Going)

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-INTERJURISDICTIONAL ROADS AND/OR BRIDGES(OR, ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)-CONSTRUCTION OF ROAD,MIISI-BONGA-BUYUAN-LIDONG-DARAGA,DARAGA/

Region V, Region V

2022₱288.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG MAG-ASAWANG TUBIG RIVER, BRGY. TAGUMPAY, PHASE I, NAUJAN, OR. MINDORO

Region IV-B, Region IV-B

2024₱287.2M
Past target date (DPWH On-Going)
View all 738 projects →

4. Implementation

Contract Amount

₱511,892,618.99

Progress

Past target date (DPWH On-Going)

Start Date

February 27, 2023

Target End

November 27, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.