Flood Control and Drainage25OB0135

CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG LABASAN RIVER (EAST BANK), PHASE 1, PACKAGE 4, TAGUIG CITY

CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG LABASAN RIVER (EAST BANK), PHASE 1, PACKAGE 4, TAGUIG CITY is a DPWH-tracked public work in Metro Manila 1st DEO, National Capital Region. Reported contract value: ₱94,550,713.33. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: RVR3 CONST SUPPLY AND SERVICES. Figures trace to dpwh.

Metro Manila 1st DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱23,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction (Completion) of Flood Control Structure along Ermitaño Creek, Barangay Addition Hills, San Juan City
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Metro Manila 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱94,550,713.33

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

February 18, 2025

Target End

October 15, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.