Flood Control and Drainage25OF0152

CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG TULLAHAN RIVER AND TRIBUTARIES (PHASE 3), BARANGAY NOVALICHES PROPER, QUEZON CITY

CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG TULLAHAN RIVER AND TRIBUTARIES (PHASE 3), BARANGAY NOVALICHES PROPER, QUEZON CITY is a DPWH-tracked public work in Quezon City 1st DEO, National Capital Region. Reported contract value: ₱94,550,574.00. Status: Past target date (DPWH On-Going). Contractor on record: RVR3 CONST SUPPLY AND SERVICES. Figures trace to dpwh.

Quezon City 1st DEO, National Capital Region
Region: National Capital Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Structure and Tributaries at Barangay Payatas (Phase 9), Quezon City
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Quezon City 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱94,550,574.00

Progress

Past target date (DPWH On-Going)

Start Date

May 20, 2025

Target End

May 14, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.