Flood Control and Drainage17GE0029

CONSTRUCTION OF RIVER CONTROL SYSTEM AND SLOPE PROTECTION WORKS AT SALVACION RIVER, SALVACION, NUEVA VALENCIA, GUIMARAS

CONSTRUCTION OF RIVER CONTROL SYSTEM AND SLOPE PROTECTION WORKS AT SALVACION RIVER, SALVACION, NUEVA VALENCIA, GUIMARAS is a DPWH-tracked public work in Guimaras DEO, Region VI. Reported contract value: ₱9,308,974.01. Status: Reported complete (DPWH). Contractor on record: S T SALCEDO CONST CORP FORMERLY: SHAK CONST. Figures trace to dpwh.

Guimaras DEO, Region VI
Region: Region VI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱5,500,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control and Drainage System, Zaldivar, Buenavista, Guimaras
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-17-0012440

₱7,553,738.00 · FY2017

Released to Division of Butuan City (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱9,308,974.01

Progress

Reported complete (DPWH)

Start Date

June 7, 2017

Target End

December 5, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.