Roads22DH0007

ROAD WIDENING - SECONDARY ROADS, RIZAL BDRY.-FAMY-QUEZON RD., K0072 + 709-K0073 + 500, K0083 + 650-K0085 + 204, MABITAC, LAGUNA, SINILOAN, LAGUNA

ROAD WIDENING - SECONDARY ROADS, RIZAL BDRY.-FAMY-QUEZON RD., K0072 + 709-K0073 + 500, K0083 + 650-K0085 + 204, MABITAC, LAGUNA, SINILOAN, LAGUNA is a DPWH-tracked public work in Laguna 1st DEO, Region IV-A. Reported contract value: ₱93,326,411.74. Status: Reported complete (DPWH). Contractor on record: ALAGON CONST. Figures trace to dpwh.

Laguna 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 79%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Revetment/Floodwall (Staggered), Bi±an City, Laguna
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Laguna 1st DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱93,326,411.74

Progress

Reported complete (DPWH)

Start Date

March 18, 2022

Target End

November 30, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.