Roads20BB0044

CONVERGENCE&SPECIAL SUPPORT PROG-CONSTRUCTION/IMPROVT OF ACCESS RDS LEADING TO TRADES, INDUSTRIES&ECONOMICS ZONES-CONST OF CONC RD-ACCESS RD LEADING TO FISH LANDING& BAGOONG PROCESSING, SITIO NAMUYUCAN,SAN JOSE, GONZAGA,CAG, BRGY.SAN JOSE, GONZAGA,CAGAYAN

CONVERGENCE&SPECIAL SUPPORT PROG-CONSTRUCTION/IMPROVT OF ACCESS RDS LEADING TO TRADES, INDUSTRIES&ECONOMICS ZONES-CONST OF CONC RD-ACCESS RD LEADING TO FISH LANDING& BAGOONG PROCESSING, SITIO NAMUYUCAN,SAN JOSE, GONZAGA,CAG, BRGY.SAN JOSE, GONZAGA,CAGAYAN is a DPWH-tracked public work in Cagayan 1st DEO, Region II. Reported contract value: ₱7,603,242.08. Status: Reported complete (DPWH). Contractor on record: F P TABBADA CONST. Figures trace to dpwh.

Cagayan 1st DEO, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Appagonan River and its confluence along Cagayan River (Phase 10), Aparri, Cagayan
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Cagayan 1st DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

26 projects · ₱149.5M total · 0 flags

4. Implementation

Contract Amount

₱7,603,242.08

Progress

Reported complete (DPWH)

Start Date

February 12, 2020

Target End

May 11, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.