Flood Control and Drainage20AA0209

CONSTRUCTION OF VARIOUS FLOOD CONTROL STRUCTURE, BARANGAYS 07 SAN PEDRO II, 35 PIPIAS AND 03 SAN ANDRES II, AND REHABILITATION OF VARIOUS FLOOD CONTROL STRUCTURES, BARANGAYS 09 SAN AGUSTIN II, 17 STO. CRISTO I, 14 SAN GABRIEL II, 06 SAN PEDRO I, 18 STO. C

CONSTRUCTION OF VARIOUS FLOOD CONTROL STRUCTURE, BARANGAYS 07 SAN PEDRO II, 35 PIPIAS AND 03 SAN ANDRES II, AND REHABILITATION OF VARIOUS FLOOD CONTROL STRUCTURES, BARANGAYS 09 SAN AGUSTIN II, 17 STO. CRISTO I, 14 SAN GABRIEL II, 06 SAN PEDRO I, 18 STO. C is a DPWH-tracked public work in Ilocos Norte 1st DEO, Region I. Reported contract value: ₱3,749,551.63. Status: Reported complete (DPWH). Contractor on record: NORTHLANDER CONST. Figures trace to dpwh.

Ilocos Norte 1st DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 94%

UACS
18001
Amount
₱3,790,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Various Flood Control Structure, Barangays 07 San Pedro II, 35 Pipias and 03 San Andres II, and Rehabilitation of Various Flood Control Structures, Barangays 09 San Agustin II, 17 Sto. Cristo I, 14 San Gabriel II, 06 San Pedro I, 18 Sto. Cristo II and 10 San Vicente, Bacarra, Ilocos Norte
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Ilocos Norte 1st DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

72 projects · ₱564.7M total · 0 flags

4. Implementation

Contract Amount

₱3,749,551.63

Progress

Reported complete (DPWH)

Start Date

October 16, 2020

Target End

December 14, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.