Construction of Flood Mitigation Structure24KC0010

Construction of Flood Mitigation Structure along Cagayan de Oro City-Dominorog-Camp Kibaritan Rd, Downstream of Uguiban Bridge, Talakag, Bukidnon

Construction of Flood Mitigation Structure along Cagayan de Oro City-Dominorog-Camp Kibaritan Rd, Downstream of Uguiban Bridge, Talakag, Bukidnon is a DPWH-tracked public work in TALAKAG (BUKIDNON), BUKIDNON, Region X. Reported contract value: ₱49,000,000.00. Status: Reported complete (DPWH). Contractor on record: RAMISES CONST. Figures trace to sumbong.

TALAKAG (BUKIDNON), BUKIDNON, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 97%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Cagayan de Oro City - Dominorog - Camp Kibaritan Rd, Downstream of Uguiban Bridge, Talakag, Bukidnon
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROX-24-0008935

₱1,772,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROX-24-0008937

₱164,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROX-24-0017111

₱125,524.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱49,000,000.00

Progress

Reported complete (DPWH)

Start Date

February 16, 2024

Target End

January 25, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.