Water Provision and Storage16IH0084

CLUSTER 18-CONSTRUCTION OF RAINWATER COLLECTION SYSTEM(RWCS), 9 PROJECTS WITHIN THE MUNICIPALTY OF LAVEZARES & ALLEN, N. SAMAR

CLUSTER 18-CONSTRUCTION OF RAINWATER COLLECTION SYSTEM(RWCS), 9 PROJECTS WITHIN THE MUNICIPALTY OF LAVEZARES & ALLEN, N. SAMAR is a DPWH-tracked public work in Northern Samar 1st DEO, Region VIII. Reported contract value: ₱1,337,975.36. Status: Reported complete (DPWH). Contractor on record: C A CONST AND SUPPLY. Figures trace to dpwh.

Northern Samar 1st DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱1,337,975.36

Progress

Reported complete (DPWH)

Start Date

May 29, 2017

Target End

August 11, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.