Roads18IH0002

ROAD WIDENING - CATARMAN - LAOANG ROAD, K0744+(-100)-K0744+245, K0744+269-K0745+538, CATARMAN, N. SAMAR

ROAD WIDENING - CATARMAN - LAOANG ROAD, K0744+(-100)-K0744+245, K0744+269-K0745+538, CATARMAN, N. SAMAR is a DPWH-tracked public work in Northern Samar 1st DEO, Region VIII. Reported contract value: ₱45,549,407.19. Status: Reported complete (DPWH). Contractor on record: C A CONST AND SUPPLY. Figures trace to dpwh.

Northern Samar 1st DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱39,953,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Catubig River Control, Catubig, Northern Samar
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-18-0025152

₱0.00 · FY2018

Released to Surigao del Norte National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱45,549,407.19

Progress

Reported complete (DPWH)

Start Date

April 3, 2018

Target End

January 13, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.