Bridges18IK0057

WIDENING OG PERMANENT BRIDGES, APOLOGON BRIDGE ALONG DAANG MAHARLIKA

WIDENING OG PERMANENT BRIDGES, APOLOGON BRIDGE ALONG DAANG MAHARLIKA is a DPWH-tracked public work in Samar 2nd DEO, Region VIII. Reported contract value: ₱18,238,619.68. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: FRD CONST 10227. Figures trace to dpwh.

Samar 2nd DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱18,238,619.68

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

May 8, 2018

Target End

October 4, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.