Flood Control Structures, Roads24IM0078

REHABILITATION OF ROAD WITH DRAINAGE, TACLOBAN NORTH RESETTLEMENT, GUADALUPE HEIGHTS 1, TACLOBAN CITY, LEYTE

REHABILITATION OF ROAD WITH DRAINAGE, TACLOBAN NORTH RESETTLEMENT, GUADALUPE HEIGHTS 1, TACLOBAN CITY, LEYTE is a DPWH-tracked public work in Tacloban City DEO, Region VIII. Reported contract value: ₱49,473,173.05. Status: Past target date (DPWH On-Going). Contractor on record: FAIRCHILD BUILDERS & DEVELOPERS INC. Figures trace to dpwh.

Tacloban City DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure ( Drainage System ) , Barangay 63, Tacloban City, Leyte
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Tacloban City DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Other projects by this contractor

No sat.

SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES CONSTRUCTION OF ROAD, BURAUEN, LEYTE

Region VIII, Region VIII

2022₱286.3M
Past target date (DPWH On-Going)
No sat.

CLUSTER 1: 1. CONSTRUCTION OF ROCK GUARD SLOPE PROTECTION ALONG BURAUEN - MAHAGNAO ROAD, K0988+780 - K0989+020, BURAUEN, LEYTE; AND TWO (2) OTHER LOCATIONS IN BURAUEN, LEYTE

Region VIII, Region VIII

2020₱283.4M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - TERTIARY ROADS - BURAUEN - MAHAGNAO RD. - K0989+685 - K0989+810, BURAUEN, LEYTE

Region VIII, Region VIII

2021₱144.7M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - TERTIARY ROADS - BURAUEN - MAHAGNAO RD. - K0989+560 - K0989+685, BURAUEN, LEYTE

Region VIII, Region VIII

2021₱144.7M
Reported complete (DPWH)
No sat.

SIPAG - ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - ROAD OPENING AND CONCRETING OF BURAUEN SOUTHEAST SEMI-CIRCUMFERENTIAL ROAD TRAVERSING BRGY. POBLACION

Region VIII, Region VIII

2023₱144.7M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF (RCDG) REINFORCED CONCRETE DECK GIRDER BRIDGE FROM BARANGAY MAHAGN

Region VIII, Region VIII

2024₱144.7M
Past target date (DPWH On-Going)
View all 42 projects →

4. Implementation

Contract Amount

₱49,473,173.05

Progress

Past target date (DPWH On-Going)

Start Date

September 6, 2024

Target End

April 24, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.