Flood Control and Drainage17OC0048

UPGRADING OF DRAINAGE SYSTEM ALONG DOÑA SOLEDAD EXT., BARANGAY DON BOSCO,PARAÑAQUE CITY 2ND LD, METRO MANILA

UPGRADING OF DRAINAGE SYSTEM ALONG DOÑA SOLEDAD EXT., BARANGAY DON BOSCO,PARAÑAQUE CITY 2ND LD, METRO MANILA is a DPWH-tracked public work in Metro Manila 2nd DEO, National Capital Region. Reported contract value: ₱10,514,322.00. Status: Reported complete (DPWH). Contractor on record: B C CUERPO CONST CORP. Figures trace to dpwh.

Metro Manila 2nd DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Flood Control: Construction of Riverwall along Tullahan, Barangay 164, Caloocan City
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-17-0004339

₱0.00 · FY2017

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

56 projects · ₱3.7B total · 0 flags

Other projects by this contractor

No sat.

LOCAL PROGRAM, NATIONAL BUILDING PROGRAM, BUILDINGS AND OTHER STRUCTURES - MULTI-PURPOSE/FACILITIES, CONSTRUCTION OF PCOO VISAYAS HUB BUILDING IN BARANGAY SUBANGDAKU, MANDAUE CITY

Region VII, Region VII

2022₱289.5M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS DARAGA, ALBAY DIVERSION ROAD, ALBAY, DARAGA, ALBAY PROVINCE

Region V, Region V

2018₱217.8M
Reported complete (DPWH)
No sat.

WIDENING OF PUERTO PRINCESA SOUTH ROAD FROM TWO(2) TO SIX (6) LANES INCL DRAINAGE STRUCTRES AND OTHER ANCILLARY WORKS K0110+400-K0110+740; K0111+300-K0111+439; K0111+455-K0111+677; K0111+693-K0113+714; K0113+736-K0113+770, NARRA, PALAWAN

Region IV-B, Region IV-B

2018₱144.8M
Reported complete (DPWH)
No sat.

ROAD OPENING/CONCRETING OF CONCEPTION - TAPUL - NAWL - PAGSANGHAN - ANAGASE - STO. NIÑO - MAYDOLOBE - SARAO CANVALS - CARANAS ROAD, PARANAS - MOTIONG SAMAR (PHASE I), SAMAR 2ND LD

Region VIII, Region VIII

2020₱143.9M
Past target date (DPWH On-Going)
No sat.

ROAD OPENING/CONCRETING OF CONCEPTION - TAPUL - NAWL - PAGSANGHAN - ANAGASE - STO. NIÑO - MAYLOBE - SARAO CANVAIS - CARANAS ROAD, PARANAS - MOTIONG, SAMAR (PHASE II), SAMAR 2ND LD

Region VIII, Region VIII

2020₱143.9M
Past target date (DPWH On-Going)
No sat.

ROAD WIDENING - BILIRAN CIRCUMFERENTIAL ROAD, K1008+360-K1010+490, K1011+480-K1011+690, K1011+740-K1012+093,K1012+134-K1013+490 (11.4738, 124.4695-11.4788, 124.5436, 11.4862, 124.4503-11.4878, 124.4495, 11.4882, 124.4494-11.4912,..,PROVINCE OF BILIRAN

Biliran DEO, Region VIII

2018₱139.6M
Reported complete (DPWH)
View all 56 projects →

4. Implementation

Contract Amount

₱10,514,322.00

Progress

Reported complete (DPWH)

Start Date

April 16, 2017

Target End

October 12, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.