Roads18L00002

WIDENING (4 INTO 6 LANES) OF DIGOS-MAKAR RD INCLUDING RROW (GUIHING & NORTHERN PALIGUE-HARADA BUTAI

WIDENING (4 INTO 6 LANES) OF DIGOS-MAKAR RD INCLUDING RROW (GUIHING & NORTHERN PALIGUE-HARADA BUTAI is a DPWH-tracked public work in Region XI, Region XI. Reported contract value: ₱112,783,784.58. Status: Reported complete (DPWH). Contractor on record: MAC BUILDERS CORP FORMERLY: MAC BUILDERS DEVELOPMENT CORP. Figures trace to dpwh.

Region XI, Region XI
Region: Region XI

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2018 GAA. DBM GAA FY2018

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱112,783,784.58

Progress

Reported complete (DPWH)

Start Date

April 29, 2018

Target End

February 16, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.