Bridges18NB0061

WIDENING OF PERMANENT BRIDGE BAYUGAN RELIEF BR. (B00903MN) ALONG DAANG MAHARLIKA (AGUSAN DAVAO SECTION), BAYUGAN, AGUSAN DEL SUR

WIDENING OF PERMANENT BRIDGE BAYUGAN RELIEF BR. (B00903MN) ALONG DAANG MAHARLIKA (AGUSAN DAVAO SECTION), BAYUGAN, AGUSAN DEL SUR is a DPWH-tracked public work in Agusan del Sur 1st DEO, Region XIII. Reported contract value: ₱19,399,929.36. Status: Reported complete (DPWH). Contractor on record: MADYAW CONST. Figures trace to dpwh.

Agusan del Sur 1st DEO, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Hamogaway Flood Control Structure including River Training (Downstream) along Daang Maharlika (Agusan - Davao Section), K0000+000 - K0000+268, Bayugan, Agusan del Sur
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-18-0003691

₱0.00 · FY2018

Released to Division of Agusan del Sur (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱19,399,929.36

Progress

Reported complete (DPWH)

Start Date

August 14, 2018

Target End

July 7, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.