Roads23BH0248

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONCRETING OF ROAD, BRGY. DABUBU GRANDE, SAN AGUSTIN, ISABELA

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONCRETING OF ROAD, BRGY. DABUBU GRANDE, SAN AGUSTIN, ISABELA is a DPWH-tracked public work in Isabela 4th DEO, Region II. Reported contract value: ₱9,644,579.16. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: NTL BUILDERS AND DEVELOPER. Figures trace to dpwh.

Isabela 4th DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Gumbaun-San Isidro Flood Control Project, Echague - San Isidro, Isabela
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Isabela 4th DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

179 projects · ₱4.0B total · 0 flags

4. Implementation

Contract Amount

₱9,644,579.16

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

December 11, 2023

Target End

April 15, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.