GAA 2025 SSP25BE0116

CONVERGENCE AND SPECIAL SUPPORT PROGRAM- BASIC INFRASTRUCTURE PROGRAM (BIP)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF BRIDGE AND INSTALLATION OF RC PIPES IN BARANGAY CAM

CONVERGENCE AND SPECIAL SUPPORT PROGRAM- BASIC INFRASTRUCTURE PROGRAM (BIP)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF BRIDGE AND INSTALLATION OF RC PIPES IN BARANGAY CAM is a DPWH-tracked public work in Isabela 1st DEO, Region II. Reported contract value: ₱9,602,528.80. Status: Past target date (DPWH On-Going). Contractor on record: RSKC CONST. Figures trace to dpwh.

Isabela 1st DEO, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Barangay Simanu Sur, San Pablo, Isabela
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Isabela 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱9,602,528.80

Progress

Past target date (DPWH On-Going)

Start Date

July 14, 2025

Target End

January 28, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.