Buildings and Facilities16NG0032

CONSTRUCTION OF COVERED COURT, GENERAL LUNA CENTRAL ELEMENTARY SCHOOL ( PHASE II ), BRGY. UNO, GENERAL LUNA, SURIGAO DEL NORTE

CONSTRUCTION OF COVERED COURT, GENERAL LUNA CENTRAL ELEMENTARY SCHOOL ( PHASE II ), BRGY. UNO, GENERAL LUNA, SURIGAO DEL NORTE is a DPWH-tracked public work in Surigao del Norte 1st DEO, Region XIII. Reported contract value: ₱1,976,962.88. Status: Reported complete (DPWH). Contractor on record: ZI 9 BUILDERS AND SUPPLIES. Figures trace to dpwh.

Surigao del Norte 1st DEO, Region XIII
Region: Region XIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction / Rehabilitation of General Luna Flood Control Structures, Brgy. Pob. 3, General Luna, Surigao del Norte 1st LD
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-16-0031166

₱808,520.00 · FY2016

Released to Division of Samar (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

104 projects · ₱548.7M total · 0 flags

4. Implementation

Contract Amount

₱1,976,962.88

Progress

Reported complete (DPWH)

Start Date

November 2, 2016

Target End

December 31, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.