Roads22A00072

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - CONSTRUCTION OF THE VILLA VERDE ROAD CONNECTING THE PROVINCES OF NUEVA VIZCAYA AND PANGASINAN

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - CONSTRUCTION OF THE VILLA VERDE ROAD CONNECTING THE PROVINCES OF NUEVA VIZCAYA AND PANGASINAN is a DPWH-tracked public work in Region I, Region I. Reported contract value: ₱96,499,340.33. Status: Reported complete (DPWH). Contractor on record: AQUINO-DELA CRUZ ENGINEERING. Figures trace to dpwh.

Region I, Region I
Region: Region I

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2022 GAA. DBM GAA FY2022

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱96,499,340.33

Progress

Reported complete (DPWH)

Start Date

April 8, 2022

Target End

May 18, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.