Water Provision and Storage20FI0047

CLUSTER I - CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTOR IN PUBLIC FACILITIES AT BALUD, MASBATE. A. BONGCANAWAY ES, BALUD, MASBATE, B. GUINBANUAHAN ES, BALUD, MASBATE, C. ENRIQUE BAYOLA SR. MHS, BALUD, MASBATE

CLUSTER I - CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTOR IN PUBLIC FACILITIES AT BALUD, MASBATE. A. BONGCANAWAY ES, BALUD, MASBATE, B. GUINBANUAHAN ES, BALUD, MASBATE, C. ENRIQUE BAYOLA SR. MHS, BALUD, MASBATE is a DPWH-tracked public work in Masbate 2nd DEO, Region V. Reported contract value: ₱831,089.74. Status: Reported complete (DPWH). Contractor on record: JRMG CONST AND SUPPLY. Figures trace to dpwh.

Masbate 2nd DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control System along Lumbang River, Masbate City
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Masbate 2nd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

20 projects · ₱110.1M total · 0 flags

4. Implementation

Contract Amount

₱831,089.74

Progress

Reported complete (DPWH)

Start Date

August 30, 2020

Target End

October 28, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.