Construction of Flood Mitigation Structure22FA0045

Construction of Flood Control at Barangay Calbayog and Barangay San Roque, Malilipot, Albay

Construction of Flood Control at Barangay Calbayog and Barangay San Roque, Malilipot, Albay is a DPWH-tracked public work in MALILIPOT (ALBAY), ALBAY, Region V. Reported contract value: ₱44,100,000.00. Status: Reported complete (DPWH). Contractor on record: 3DIAMONDS CONST CORP. Figures trace to sumbong.

MALILIPOT (ALBAY), ALBAY, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱45,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control at Barangay Calbayog and Barangay San Roque, Malilipot, Albay
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003098

₱142,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003135

₱141,500,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003044

₱135,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003055

₱46,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

69 projects · ₱3.1B total · 0 flags

Other projects by this contractor

Construction/Improvement/Rehabilitation of Nasisi River Flood Mitigation Structure (Barangay Batang, Barangay Herrera, and Barangay Pinit), Ligao City, Albay

CITY OF LIGAO (ALBAY), ALBAY, Region V

2023₱115.8M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-PRIMARY ROADS-MAHARLIKA HIGHWAY-K0505+419-K0505+600, K0509+704-K0510+912, GUINOBATAN, ALBAY (3RD LEGISLATIVE DISTRICT)

Region V, Region V

2025₱100.2M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM(BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES- CONSTRUCTION OF SAN FRANCISCO RIVER FLOOD MITIGATION STRUCTURES, BRGY. MAGUIRON AND BRGY. M

Albay 3rd DEO, Region V

2024₱99.0M
Past target date (DPWH On-Going)
No sat.

CLUSTER V-2022: 1.) REHABILITATION OF TANDARORA FLOOD CONTROL DIKE (LEFT SIDE) GUINOBATAN, ALBAY; AND 2.) REHABILITATION OF TANDARORA FLOOD CONTROL DIKE (RIGHT SIDE) GUINOBATAN, ALBAY

Albay 3rd DEO, Region V

2022₱98.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF NASISI RIVER FLOOD MITIGATION STRUCTURE, BARANGAY NABONTON, LIGAO CITY, ALBAY

Albay 3rd DEO, Region V

2024₱96.2M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF FLOOD MITIGATION RIVERBANK CONTROL STRUCTURE ALON

Albay 3rd DEO, Region V

2025₱94.1M
Past target date (DPWH On-Going)
View all 69 projects →

4. Implementation

Contract Amount

₱44,100,000.00

Progress

Reported complete (DPWH)

Start Date

August 5, 2022

Target End

January 29, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.