Flood Control and Drainage25GD0003

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF FLOOD MITIGATION FACILITIES ALONG PANAY/MAMBUSAO RIVER BASIN, TALASA RIVER CONTROL, BRGY, TALASA, PANAY, CAPIZ

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF FLOOD MITIGATION FACILITIES ALONG PANAY/MAMBUSAO RIVER BASIN, TALASA RIVER CONTROL, BRGY, TALASA, PANAY, CAPIZ is a DPWH-tracked public work in Capiz 1st DEO, Region VI. Reported contract value: ₱56,260,124.59. Status: Past target date (DPWH On-Going). Contractor on record: JELSIE CONST. Figures trace to dpwh.

Capiz 1st DEO, Region VI
Region: Region VI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Facilities along Panay/Mambusao River Basin, Tico River Control, Panay, Capiz
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Capiz 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

62 projects · ₱4.1B total · 0 flags

Other projects by this contractor

No sat.

RETROFITTING OF MULTI-PURPOSE BUILDING, ISABELO DELOS REYES ELEMENTARY SCHOOL, MANILA CITY

North Manila DEO, National Capital Region

2025₱145.8M
Past target date (DPWH On-Going)
No sat.

RETROFFITING OF SCHOOL BUILDING AT LEGARDA ELEMENTARY SCHOOL, MANILA

North Manila DEO, National Capital Region

2025₱145.7M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING, SENTRO KOMUNIUDAD DE SANTA CRUZ, MANILA (PHASE 1)

North Manila DEO, National Capital Region

2025₱145.5M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2:PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS-FLOOD MGM'T PROGRAM-CONST./MAINT. OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEMS-CONST. OF SLOPE PROTECTION STRUCTURE AT BASECO COMPOUND, PORT AREA, MANILA, PHASE 6

South Manila DEO, National Capital Region

2025₱143.1M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2:PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS-FLOOD MGM'T PROGRAM-CONST./MAINT. OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEMS-CONST. OF SLOPE PROTECTION STRUCTURE, PHASE 5, BASECO COMPOUND, PORT AREA, MANILA

South Manila DEO, National Capital Region

2025₱143.0M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2:PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS-FLOOD MGM'T PROGRAM-CONST./MAINT. OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEMS-CONST. OF SLOPE PROTECTION STRUCTURE AT BASECO COMPOUND, PORT AREA, MANILA, PHASE 7

South Manila DEO, National Capital Region

2025₱142.9M
Past target date (DPWH On-Going)
View all 62 projects →

4. Implementation

Contract Amount

₱56,260,124.59

Progress

Past target date (DPWH On-Going)

Start Date

March 17, 2025

Target End

January 25, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.