Flood Control and Drainage25OH0029

ORGANIZATIONAL OUTCOME 2:PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS-FLOOD MGM'T PROGRAM-CONST./MAINT. OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEMS-CONST. OF SLOPE PROTECTION STRUCTURE, PHASE 5, BASECO COMPOUND, PORT AREA, MANILA

ORGANIZATIONAL OUTCOME 2:PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS-FLOOD MGM'T PROGRAM-CONST./MAINT. OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEMS-CONST. OF SLOPE PROTECTION STRUCTURE, PHASE 5, BASECO COMPOUND, PORT AREA, MANILA is a DPWH-tracked public work in South Manila DEO, National Capital Region. Reported contract value: ₱143,013,053.73. Status: Past target date (DPWH On-Going). Contractor on record: JELSIE CONST. Figures trace to dpwh.

South Manila DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 77%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Estero de Sunog Apog, Barangay 172, Manila City
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

South Manila DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

62 projects · ₱4.1B total · 0 flags

4. Implementation

Contract Amount

₱143,013,053.73

Progress

Past target date (DPWH On-Going)

Start Date

March 3, 2025

Target End

November 27, 2025

5. Audit