Flood Control and Drainage24K00518

CONST. OF MALA-LAWASAIG RIVER FLOOD CONTROL AND SLOPE PROTECTION, BARANGAY SUGOD,BAYABAO SECTION, DITSAAN RAMAIN, LANAO DEL SUR

CONST. OF MALA-LAWASAIG RIVER FLOOD CONTROL AND SLOPE PROTECTION, BARANGAY SUGOD,BAYABAO SECTION, DITSAAN RAMAIN, LANAO DEL SUR is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱47,765,556.43. Status: Past target date (DPWH On-Going). Contractor on record: M M A ACHIEVER CONST. Figures trace to dpwh.

Region X, Region X
Region: Region X

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱47,765,556.43

Progress

Past target date (DPWH On-Going)

Start Date

January 2, 2025

Target End

October 28, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.