Flood Control and Drainage19DK0034

CONSTRUCTION OF FLOOD MITIGATION STRUCTURES UPGRADING OF SPILLWAY BARANGAY SAN RAFAEL, MAUBAN, QUEZON

CONSTRUCTION OF FLOOD MITIGATION STRUCTURES UPGRADING OF SPILLWAY BARANGAY SAN RAFAEL, MAUBAN, QUEZON is a DPWH-tracked public work in Quezon 1st DEO, Region IV-A. Reported contract value: ₱9,800,000.00. Status: Reported complete (DPWH). Contractor on record: ZELAN CONST AND SUPPLY INC FORMERLY: ZELAN CONST AND SUPPLY. Figures trace to dpwh.

Quezon 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-B-19-0004171

₱46,809,683.00 · FY2019

Released to Jose R. Reyes Memorial Medical Center (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

80 projects · ₱502.6M total · 0 flags

4. Implementation

Contract Amount

₱9,800,000.00

Progress

Reported complete (DPWH)

Start Date

July 3, 2019

Target End

November 27, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.