GAA 2025 OO-225CD0035

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MEYCAUAYAN RIVER, LIPUTAN - NAGBALON SECTION, STA. 05+475 - STA. 05+575, MEYCAUAYAN, BULACAN

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MEYCAUAYAN RIVER, LIPUTAN - NAGBALON SECTION, STA. 05+475 - STA. 05+575, MEYCAUAYAN, BULACAN is a DPWH-tracked public work in Bulacan 2nd DEO, Region III. Reported contract value: ₱96,493,804.35. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: JB CONST AND SUPPLY INC FORMERLY:JB CONST AND SUPPLY. Figures trace to dpwh.

Bulacan 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Meycauayan River, Sta. 04+575-Sta. 04+675 (Liputan – Nagbalon Section), Meycauayan, Bulacan
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Bulacan 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

74 projects · ₱3.5B total · 2 flags

4. Implementation

Contract Amount

₱96,493,804.35

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

February 24, 2025

Target End

November 7, 2025

5. Audit