Roads25DM0160

CONCRETING OF BRGY. BULO ILAYA TO BRGY. BURGOS TO BRGY. MAIROK ILAYA TO BRGY. MAIROK IBABA FMR, UNISAN, QUEZON

CONCRETING OF BRGY. BULO ILAYA TO BRGY. BURGOS TO BRGY. MAIROK ILAYA TO BRGY. MAIROK IBABA FMR, UNISAN, QUEZON is a DPWH-tracked public work in Quezon 3rd DEO, Region IV-A. Reported contract value: ₱24,826,819.39. Status: Past target date (DPWH On-Going). Contractor on record: R A MENDIOLA CONST. Figures trace to dpwh.

Quezon 3rd DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation, Structure along Bingabing Creek, Brgy. Madulao, Catanauan, Quezon
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Quezon 3rd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

467 projects · ₱8.0B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES 14. CONSTRUCTION OF ROAD, GUMACA, QUEZON,

Quezon 4th DEO, Region IV-A

2023₱106.2M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES 18. CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD

Quezon 4th DEO, Region IV-A

2023₱106.2M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES 15. CONSTRUCTION/IMPROVEMENT OF ACCESS ROA

Quezon 4th DEO, Region IV-A

2023₱106.2M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES 16. CONSTRUCTION OF ROAD, GUINAYANGAN, QUE

Quezon 4th DEO, Region IV-A

2023₱106.2M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF FLOOD CONTROL, BARANGAY 1 AND BARANGAY 5, CATANAUAN, QUEZON

Quezon 3rd DEO, Region IV-A

2024₱101.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM, ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES 7. CONSTRUCTION OF LOPEZ -MACALELON ROAD, PACKAGE E, LOPEZ, QUEZON

Quezon 4th DEO, Region IV-A

2023₱99.0M
Reported complete (DPWH)
View all 467 projects →

4. Implementation

Contract Amount

₱24,826,819.39

Progress

Past target date (DPWH On-Going)

Start Date

August 18, 2025

Target End

February 13, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.