Buildings and Facilities25KA0023

CONSTRUCTION OF MULTI-PURPOSE BUILDING,BARANGAY CAPITAN ANGEL, MALAYBALAY CITY, BUKIDNON BARANGAY CAPITAN ANGEL, MALAYBALAY CITY, BUKIDNON 2ND LD

CONSTRUCTION OF MULTI-PURPOSE BUILDING,BARANGAY CAPITAN ANGEL, MALAYBALAY CITY, BUKIDNON BARANGAY CAPITAN ANGEL, MALAYBALAY CITY, BUKIDNON 2ND LD is a DPWH-tracked public work in Bukidnon 1st DEO, Region X. Reported contract value: ₱5,929,633.84. Status: Reported complete (DPWH). Contractor on record: LIMBO CONST. Figures trace to dpwh.

Bukidnon 1st DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Barangay Miglamin, Malaybalay City, Bukidnon
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Bukidnon 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

7 projects · ₱45.8M total · 0 flags

4. Implementation

Contract Amount

₱5,929,633.84

Progress

Reported complete (DPWH)

Start Date

January 24, 2025

Target End

July 27, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.