Roads20J00037

CONSTRUCTION OF CONCRETE ROAD NRJ AYALA - LA PAZ ROAD LEADING TO LA PAZ RESORT, ZAMBOANGA CITY

CONSTRUCTION OF CONCRETE ROAD NRJ AYALA - LA PAZ ROAD LEADING TO LA PAZ RESORT, ZAMBOANGA CITY is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱104,500,000.00. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: RABBIT CONST. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2020 GAA. DBM GAA FY2020

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

10 projects · ₱755.2M total · 0 flags

Other projects by this contractor

No sat.

CONCRETING OF ROAD FROM JUNCTION NATIONAL HIGHWAY TO AYALA - LA PAZ ROAD LEADING TO LA PAZ RESORT, ZAMBOANGA CITY (1ST DISTRICT) STA 1973 +324.24 TO STA 1978 + 215.29; ON SLD STA 1978+215.29 TO STA 1979 + 220 (NET LENGTH = 5,735.76 LN.M.)

Region IX, Region IX

2016₱144.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS - NRJ AYALA - LA PAZ ROAD LEADING TO LA PAZ RESORT, ZAMBOANGA CITY

Region IX, Region IX

2021₱102.0M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONCRETING OF ROAD FROM JUNCTION HIGHWAY TO AYALA - LA PAZ ROAD LEADING TO LA PAZ RESORT (PACKAGE II), ZAMBOANGA CITY, (1ST LD), STA. 1971+160.00 - STA. 1973+324.50, STA. 1979+060.00 - STA. 1979+690.00, NET LENGTH: 2,794.50 LN.M.

Region IX, Region IX

2017₱95.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS - NRJ AYALA - LA PAZ ROAD LEADING TO LA PAZ RESORT, ZAMBOANGA CITY

Region IX, Region IX

2018₱90.9M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS-NRJ AYALA - LA PAZ LEADING TO LA PAZ RESORT, ZAMBOANGA CITY

Region IX, Region IX

2019₱55.9M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) NRJ AYALA-LA PAZ ROAD LEADING TO LA PAZ RESORT, ZAMBOANGA CITY

Zamboanga City 2nd DEO, Region IX

2023₱48.9M
Reported complete (DPWH)
View all 10 projects →

4. Implementation

Contract Amount

₱104,500,000.00

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

March 6, 2020

Target End

August 25, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.