Roads23L00011

ROAD WIDENING - JCT. DAVAO - COTABATO RD., (MATINA CROSSING SECTION) - MATINA - APLAYA RD - JCT. TULIP DRIVE (DAVAO - COTABATO RD) - ECOLAND DRIVE - JCT. ABS-CBN QUIMPO BLVD. DIVERSION RD (JOHN PAUL SECTION), DAVAO CITY

ROAD WIDENING - JCT. DAVAO - COTABATO RD., (MATINA CROSSING SECTION) - MATINA - APLAYA RD - JCT. TULIP DRIVE (DAVAO - COTABATO RD) - ECOLAND DRIVE - JCT. ABS-CBN QUIMPO BLVD. DIVERSION RD (JOHN PAUL SECTION), DAVAO CITY is a DPWH-tracked public work in Region XI, Region XI. Reported contract value: ₱2,269,223.89. Status: Reported complete (DPWH). Contractor on record: AGONG BUILDERS AND CONST SUPPLY INC. Figures trace to dpwh.

Region XI, Region XI
Region: Region XI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱2,269,223.89

Progress

Reported complete (DPWH)

Start Date

March 22, 2023

Target End

September 16, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.