Water Provision and Storage22GN0094

CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAINWATER COLLECTOR SYSTEM - RAINWATER COLLECTOR IN PUBLIC FACILITIES 1. DOÑA HORTENCIA SALAS BENEDICTO NATIONAL HIGH SCHOOL, BRGY. POBLACION, LA CARLOTA CITY, NEGROS OCCIDENTAL, 2. NEWTON J

CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAINWATER COLLECTOR SYSTEM - RAINWATER COLLECTOR IN PUBLIC FACILITIES 1. DOÑA HORTENCIA SALAS BENEDICTO NATIONAL HIGH SCHOOL, BRGY. POBLACION, LA CARLOTA CITY, NEGROS OCCIDENTAL, 2. NEWTON J is a DPWH-tracked public work in Negros Occidental 4th DEO, Negros Island Region. Reported contract value: ₱3,454,828.20. Status: Reported complete (DPWH). Contractor on record: SILVERRIA CONST AND CONST SUPPLY CO OPC. Figures trace to dpwh.

Negros Occidental 4th DEO, Negros Island Region
Region: Negros Island Region

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Sibud Creek, Brgy. Poblacion, Bago City, Negros Occidental
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Negros Occidental 4th DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

64 projects · ₱1.2B total · 0 flags

4. Implementation

Contract Amount

₱3,454,828.20

Progress

Reported complete (DPWH)

Start Date

November 10, 2022

Target End

January 28, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.