Flood Control and Drainage25DH0019

CONSTRUCTION OF FLOOD CONTROL STRUCTURE (CALANGAY RIVER), STA. MARIA RIS, STA. MARIA, LAGUNA

CONSTRUCTION OF FLOOD CONTROL STRUCTURE (CALANGAY RIVER), STA. MARIA RIS, STA. MARIA, LAGUNA is a DPWH-tracked public work in Laguna 1st DEO, Region IV-A. Reported contract value: ₱14,251,196.50. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: R'CEL GEN CONTRACTOR. Figures trace to dpwh.

Laguna 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 95%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure (Calangay River), Sta. Maria RIS, Sta. Maria, Laguna
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Laguna 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱14,251,196.50

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

February 11, 2025

Target End

September 8, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.