Flood Control and Drainage21AC0049

CONSTRUCTION OF DRAINAGE CANAL,BRGY. NAGUILIAN, CAOAYAN, ILOCOS SUR

CONSTRUCTION OF DRAINAGE CANAL,BRGY. NAGUILIAN, CAOAYAN, ILOCOS SUR is a DPWH-tracked public work in Ilocos Sur 1st DEO, Region I. Reported contract value: ₱960,023.84. Status: Reported complete (DPWH). Contractor on record: 739 BUILDERS. Figures trace to dpwh.

Ilocos Sur 1st DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Pug-os Flood Control, Cabugao, Ilocos Sur
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Ilocos Sur 1st DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

Probable match · 94%

Construction Project

₱889,579.08 · 739 BUILDERS

Probable match · 86%

construction project

₱634,602.85 · 739 BUILDERS

Possible match · 80%

Construction Project

₱370,863.59 · 739 BUILDERS

Possible match · 79%

Construction Project

₱306,500.39 · 739 BUILDERS

Possible match · 76%

Construction Project

₱99,862.35 · 739 BUILDERS

Contractor

623 projects · ₱14.3B total · 0 flags

Other projects by this contractor

Construction of Toon-San Gregorio Flood Control Structure, La Paz, Abra

LA PAZ (ABRA), ABRA, Cordillera Administrative Region

2023₱144.7M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF DUGONG BRIDGE, BUCAY, ABRA

Abra DEO, Cordillera Administrative Region

2024₱139.7M
Past target date (DPWH On-Going)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVER, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ABRA MAJOR RIVER BASIN (PHASE II), BARANGAY BA

Abra DEO, Cordillera Administrative Region

2023₱138.1M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECT ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, REHABILITATION OF POBLACION-GAYAMAN ROAD, LUBA, ABRA

Abra DEO, Cordillera Administrative Region

2024₱138.0M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT-CONSTRUCTION OF MISSING LINKS/NEW ROADS, BESAO-TUBO (VIA TAMBOAN) ROAD, PACKAGE A, ABRA

Abra DEO, Cordillera Administrative Region

2023₱115.8M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ABRA RIVER, BARANGAY PANTAY AND BARANGAY TAMURONG, CAOAYAN, ILOCOS SUR

Ilocos Sur 1st DEO, Region I

2025₱112.3M
Past target date (DPWH On-Going)
View all 623 projects →

4. Implementation

Contract Amount

₱960,023.84

Progress

Reported complete (DPWH)

Start Date

February 26, 2021

Target End

May 3, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.