Construction of Flood Mitigation Structure23PA0047

Construction of Toon-San Gregorio Flood Control Structure, La Paz, Abra

Construction of Toon-San Gregorio Flood Control Structure, La Paz, Abra is a DPWH-tracked public work in LA PAZ (ABRA), ABRA, Cordillera Administrative Region. Reported contract value: ₱144,747,500.00. Status: Reported complete (DPWH). Contractor on record: 739 BUILDERS. Figures trace to sumbong.

LA PAZ (ABRA), ABRA, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Anislagan, Naval, Biliran
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Abra District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

623 projects · ₱14.3B total · 27 flags

Other projects by this contractor

No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF DUGONG BRIDGE, BUCAY, ABRA

Abra DEO, Cordillera Administrative Region

2024₱139.7M
Past target date (DPWH On-Going)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVER, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ABRA MAJOR RIVER BASIN (PHASE II), BARANGAY BA

Abra DEO, Cordillera Administrative Region

2023₱138.1M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECT ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, REHABILITATION OF POBLACION-GAYAMAN ROAD, LUBA, ABRA

Abra DEO, Cordillera Administrative Region

2024₱138.0M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT-CONSTRUCTION OF MISSING LINKS/NEW ROADS, BESAO-TUBO (VIA TAMBOAN) ROAD, PACKAGE A, ABRA

Abra DEO, Cordillera Administrative Region

2023₱115.8M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ABRA RIVER, BARANGAY PANTAY AND BARANGAY TAMURONG, CAOAYAN, ILOCOS SUR

Ilocos Sur 1st DEO, Region I

2025₱112.3M
Past target date (DPWH On-Going)
No sat.

REHABILITATION OF ROAD, BARANGAY CARDONA, DOLORES, ABRA

Abra DEO, Cordillera Administrative Region

2023₱99.0M
Reported complete (DPWH)
View all 623 projects →

4. Implementation

Contract Amount

₱144,747,500.00

Progress

Reported complete (DPWH)

Start Date

April 14, 2023

Target End

December 24, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.