Roads24D00053

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS CARMONA-SILANG DIVERSION ROAD, CAVITE

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS CARMONA-SILANG DIVERSION ROAD, CAVITE is a DPWH-tracked public work in Region IV-A, Region IV-A. Reported contract value: ₱33,871,500.33. Status: Past target date (DPWH On-Going). Contractor on record: MARCBILT CONST INC. Figures trace to dpwh.

Region IV-A, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

162 projects · ₱10.5B total · 0 flags

4. Implementation

Contract Amount

₱33,871,500.33

Progress

Past target date (DPWH On-Going)

Start Date

March 18, 2024

Target End

August 29, 2024