Buildings and Facilities17DD0239

COMPLETION OF FOUR (4) STOREY TWELVE (12) CLASSROOMS SCHOOL BUILDING, TAYSAN NHS, SAN JOSE, BATANGAS

COMPLETION OF FOUR (4) STOREY TWELVE (12) CLASSROOMS SCHOOL BUILDING, TAYSAN NHS, SAN JOSE, BATANGAS is a DPWH-tracked public work in Batangas 4th DEO, Region IV-A. Reported contract value: ₱2,024,220.00. Status: Reported complete (DPWH). Contractor on record: THREE W BUILDERS INC. Figures trace to dpwh.

Batangas 4th DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Improvement of Revetment with Floodwall along Downstream of Ibaan River, Ibaan, Batangas
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-E-17-0020346

₱409,941.00 · FY2017

Released to Regional Office - IV (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱2,024,220.00

Progress

Reported complete (DPWH)

Start Date

December 4, 2017

Target End

March 3, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.